Communal heating for housing associations

Most communal networks serving social housing were never designed to be measured. This article sets out the journey from where such a network is today to one that is reliable, meets the coming technical standard, reports its performance every month, and deals with faults before residents feel them. Government funding covers part of that journey, and local engineers can do most of the work on the ground.

November 2026

Who this is for

Housing associations and councils that own communal or district heat networks serving social tenants, and in particular residents who are vulnerable to cold homes, high bills or interruptions to hot water. These networks are being regulated for the first time, and the same networks are first in line for the government's efficiency funding. The two things go together: the funding exists to bring networks up to the standard they will be assessed against.

The article is written for the people who will own the decision, with the engineering kept to what matters. The videos are short recordings of the platform we use to run the work, filmed on a demonstration network.

The journey in eight minutes. From today's network to one that is reliable, compliant, reporting and alarmed, with the funding and the roles along the way.

Where most networks are today

A typical communal network of this age has a boiler house, a set of risers and laterals, and a heat interface unit in every home. It has been maintained reactively: a fault is reported, someone attends, the fault is fixed or worked around. Few of these networks can answer the questions the regulator is about to ask.

  • How much fuel goes in, how much heat reaches homes, and how much is lost on the way? On older networks the losses are commonly a third to a half of the heat generated, and residents pay for it through the tariff.
  • Which homes have hot water that takes too long to arrive, or heating that never quite reaches temperature?
  • Which parts of the system are running outside their design, and since when?
  • When something fails, who finds out, how quickly, and what happens next?

Nobody is at fault for this. The networks were built to a standard that did not require measurement, and the metering that exists was put in for billing. The point of the journey is to get from here to a network that answers these questions as a matter of routine.

Where you need to be

The destination is a network that is four things at once.

  1. Reliable. Hot water and heating arrive when residents expect them, and interruptions are rare, short and explained.
  2. Compliant. The network meets the Heat Network Technical Assurance Scheme, with the evidence to show it.
  3. Reporting. Its key performance indicators are calculated from its own meter data every month and submitted.
  4. Alarmed. When a KPI slips or a meter stops reading, that is noticed within a day, becomes an issue with a root cause, is assigned to an engineer, and is closed with evidence.

Two government schemes shape the route there, and both need a short introduction.

HNTAS, the standard you will be measured against

The Heat Network Technical Assurance Scheme (HNTAS) sets a minimum technical standard for heat networks in Great Britain under the new heat network regulations. A network is assessed element by element: the energy centre, the distribution between and within buildings, substations, and the consumer connection in each home. Each element has its own specification, its own required monitoring points and its own KPIs. The network proves it meets the standard with evidence, and then keeps proving it with monitoring and KPIs for as long as it operates.

Networks that already exist join the scheme at Milestone 4, an assessment of the network as it runs today. In the current drafts that assessment asks for around thirty named pieces of evidence, a condition survey within the previous six months, an independent inspection every year and at least three months of KPI data. The metering standard numbers every point that must be read, at five or thirty minute intervals, and a calculated value never stands in for a physical meter. A KPI breach in one reporting interval needs a justification; three in a row trigger a root-cause investigation and the works to put it right.

The documents are still drafts and the details will move, but the shape is settled: measure the network properly, assess it against the standard, report every month, and act on breaches. The full KPI set with its monitoring points and thresholds is published openly at hnqap.org/kpis.

An introduction to HNTAS (6 min). The five documents, the six life stages, the elements, and what a Milestone 4 assessment asks for.

HNES, the funding that helps you get there

The Heat Network Efficiency Scheme (HNES) is the government's grant scheme for heat networks that already exist, in England and Wales. It funds two things. Revenue funding pays for an optimisation study by an independent specialist, up to the whole of its eligible cost. Capital funding pays towards the improvement works the study identifies, up to, but not including, half of the eligible cost. Networks serving social housing and residents in need are prioritised, so a housing association with vulnerable tenants is exactly who the scheme was designed for.

Capital funding covers efficiency works on the network itself: energy centre controls, pumps, insulation and water treatment; distribution pipework and its insulation; balancing and controls inside the buildings; and sub-metering. It does not cover replacing the heat source with a low-carbon one, which has its own scheme, and costs incurred before an award cannot be claimed, so the order of events matters. The scheme runs in rounds a few times a year, with a short expression of interest followed by an online application.

An introduction to HNES (4 min). Revenue and capital funding, what is eligible, the rounds, and how an application is put together.

The journey, stage by stage

The stages below are the same whether or not grant funding is involved. What funding changes is who pays for each stage and when it can start.

Stage 1. Know the network

The first job is a record of the network as it is: every element from the boiler house to each home, the pipework between them, the meters and controls that exist, and the documents that describe it. On our platform each network becomes a site with its own data model and a 3D model of the blocks and pipework, which is also the physics model that later calculates losses and tests improvements.

From bills, meter exports and whatever drawings exist, a baseline energy balance is built in about two weeks: fuel in, heat leaving the energy centre, heat delivered to homes, and the losses in between, each figure marked measured or estimated. The same exercise produces the schedule of metering gaps against the HNTAS monitoring points, which is the first thing an assessor will want to see.

Stage 2. Survey and test, with local engineers

Next, people go and look. The energy centre, the distribution and a sample of homes are surveyed on structured forms on a phone, with photographs where the question needs them. Every check has a pass or fail rule, so a failed check becomes an issue at the moment it is found, classified against the fault library and root causes in the government's optimisation guidance.

This is where local labour earns its place. The forms carry the engineering: an engineer who knows the estate and is trusted by residents can collect evidence to a consistent standard without being a heat-network specialist, and an automatic review checks each form for gaps and odd readings before they leave the site. The office sees progress home by home on a tracker, raises queries back to the engineer, and signs the work off in stages. Where the metering cannot support the baseline, temporary monitoring goes into the plant room for the duration.

Stage 3. Fix what the survey found

The issues register is turned into works packages: groups of remedial works, each linked to the issues it closes, costed on a stated basis, and modelled on the network so the saving is a calculated figure rather than a hope. Quick wins such as control settings, bypasses and insulation are separated from capital measures such as pumps, plant controls and metering.

The works themselves can be done by the same local engineers, as jobs on the same platform: a standard works package becomes a job on a home or a riser, with its own checks and photographs, and the tracker shows what is done. Where a capital grant is involved, each package is marked eligible, partly eligible or not eligible against the scheme's categories, so the application is built from the start rather than reconstructed at the end.

Stage 4. Measure the network continuously

Reliability and compliance both depend on data arriving by itself. Daily meter reads from the metering and billing provider, points from the building management system, and any temporary monitoring are mapped once to the network's elements. From then on the HNTAS KPIs for every element are calculated each night: losses by section, flow and return temperatures, time at setpoint, meter health, and the completeness of the data itself. A monthly report comes out of the same record.

This is also the moment a housing association learns what its metering contract actually delivers. Flow rates and return temperatures are often read but never reported, and a provider that will not release live data makes several KPIs impossible to calculate. It is worth settling that before HNTAS makes it urgent.

Stage 5. Comply, and keep it that way

By this stage the Milestone 4 evidence largely exists as a by-product: the condition survey, the issues register and what was done about it, the monitoring strategy, the metering schedule, and months of KPI data. Acceptance forms, sign-offs and certificates give an assessor the audit trail without anyone assembling a binder.

Keeping it that way is what "alarmed" means in practice. Each night's KPI run flags the elements that have slipped. A failing KPI or a silent meter becomes an issue with a root cause, is assigned to an engineer as a job, and is closed with the evidence that it was fixed. A single breach is justified; a repeated one triggers the investigation the scheme requires, with the record already in place. Residents feel the difference as hot water that arrives and heating that holds, rather than as a letter about an inspection.

Paying for it: two routes through HNES

For a network with social tenants the question is rarely whether to use HNES but how to sequence it. There are two sensible routes, and the difference between them is time.

Funded study firstSelf-funded study now
Stage 1, know the networkStarts when the revenue grant is awardedStarts immediately
Stage 2 and 3, study and works packagesRevenue-funded study, up to the whole eligible cost, typically twelve weeks from awardSelf-funded study on the same platform, typically eight to twelve weeks
Capital applicationThe round after the study completesThe next round that opens
Capital grantUp to, but not including, half of eligible worksThe same
Who pays for the studyThe schemeYou, or a lighter self-funded scope
Time to works on siteTwo rounds of applications, often a year or moreOne round, often six to nine months sooner

The scheme runs rounds a few times a year, and each application is followed by an assessment period. The funded route therefore spends two of those cycles before works can start: one to win the study, one to win the capital. The self-funded route spends one. There is a point at which the savings realised sooner outweigh the study grant forgone, and for a network with large losses it comes quickly.

As an illustration only: if a network wastes £40,000 a year in heat it never delivers and the works would halve that, each month of delay costs about £1,700 in fuel alone. Bringing the works forward by nine months is worth around £15,000, before counting residents' bills, complaints and the cost of reactive call-outs. The study itself is a fraction of the capital it unlocks. Whichever route you take, the quick wins that pay back fastest can start before any award, provided that spend is kept outside the claim.

Two further points. The application needs a baseline the scheme accepts estimates for, so a network with poor metering should not wait for better metering before applying. And where a network has little social housing, capital funding is less likely, but the stages above still pay for themselves on most older networks.

Who does what

The platform is built around organisations rather than projects, and that is what makes shared delivery work.

  • The housing association has its own tenancy: its own users, its own sites, its own branding on reports, and its own data that it keeps when any study ends. Its staff see the tracker, the issues, the KPIs and the reports for every site, approve work, and download certificates.
  • Local engineers are invited into that tenancy with engineer access. They see the jobs assigned to them on the phone, work through the forms, take the photographs, raise issues and answer queries. The app works offline in plant rooms and risers and syncs when a signal returns.
  • Heatweb supports from the side: setting up the networks and their telemetry, running the HNES study and preparing the applications, reviewing survey returns, and keeping the KPI engine aligned with the standard as it moves. Where the scheme requires an independent specialist, that is us; the fieldwork can still be done by people who know the estate.

Each role sees what it needs and no more, and every change is attributed, which is what an assessor and an auditor both want.

Where to start

  1. List the networks with the number of homes, the heat source, the age, and the metering and billing arrangement for each.
  2. Register an expression of interest for the next HNES round for the networks with the most social housing; it takes ten minutes and commits you to nothing.
  3. Put one network on the platform and build its baseline from the bills and meter exports you already have. That tells you the size of the losses and the size of the metering gap, and makes both routes above concrete.
  4. Nominate the engineers who will do the surveys, and invite them.

From there the stages run in order, and the network you end up with is one that keeps telling you how it is doing.

Related reading: HNES application support, heat network monitoring and HNTAS KPIs, and the open KPI reference at hnqap.org.